Ares V timeline
By Rob Coppinger
Ares V request for proposals 5 January 2009
Concept review 21 April 2009
Phase one contracts awarded Q2 2009
Functional feasibility review 25 August 2009
Preliminary requirements review 23 March 2010
Concept design review December 2010
Level two system requirement review 2010
Level three system requirement review 2011
Authority to proceed 2011
Level three system definition review 2012
Phase two DDT&E and production contracts March 2012
Ares V elements' preliminary design review Q3 2013 to Q1 2014
Ares V elements' critical design review 2016
Ares V test flight 2018, first lunar mission December 2019